Engineering Projects: Pont sobre el Riu Valira de Orient, Zona Escoles Encamp

Infrastructure


Place:

Encamp (Principat d'Andorra)


Date: 1999
Pont sobre el Riu Valira de Orient, Zona Escoles Encamp, Engineering (Principality of Andorra)

Pont sobre el Riu Valira de Orient, Zona Escoles Encamp

The first phase of this project involved the drilling of micro piles. The second stage in the excavation of land levels to reach the design limits. The third phase consisted in the realization of the foundation.

Placed concrete, the concrete was made directly from truck mixer-pump. In the fourth phase the walls were made.

The fifth phase involved the completion of the section of slab. Placed concrete, the concrete was made directly from truck mixer-pump. In the sixth phase was the demolition.

The seventh phase involved the drilling of micro piles. The eighth phase consisted of the excavation of land levels to reach the design limits. In the phase ninth embodiment of the foundations.

Placed concrete, the concrete was made directly from truck mixer-pump. The tenth phase consisted of conducting walls. The eleventh stage was the completion of the section of slab.

For the execution of the work, definition of materials, their quality and method of measurement followed the directions in the specification of 1975 the Ministry of Public Works, Spanish, and also the "Instruction for the Design and Implementation of Concrete Works en masse and Armed "EH-91 like the post tensioned concrete corresponding to EP-91.
   
Hubieroon also factory-made items such as: concrete walls and foundations.